Project members and allocations

Manager/Admin: assign employees to a project and plan their capacity.

What this does

Manager/Admin: add or update an employee allocation role, percentage, and project dates.

Before you start

Save the project before adding a resource allocation.

Steps

  1. In Projects, use the project pencil icon and open Team & Members.
  2. Under Resource Allocation & Capacity, enter Project role, choose Select employee, set the allocation percentage and start/end dates, then select Add.
  3. Use the edit control and Save to update an allocation, or the archive control to archive it.

Result

The table shows the employee, period, allocation, capacity, availability, and status: Available, Fully Allocated, Overallocated, Schedule Unavailable, or Archived. Allocation is planned capacity, not recorded or actual time.